MP-260025 N07-76 FF-EW Bridge maintenance TG, PV Construction MK+ up to IBN, BL

Machine-translated; the original text is authoritative.

Contracting authority
Bundesamt für Strassen ASTRA - Filiale Winterthur
Place
Canton BL
Submission deadline
12.01.2027, 23:59
Published
23.11.2026
Procedure
Open procedure
Type
Service
Project number
47807
CPV code
71300000 Engineering services
Languages of the bid
German

Description

Machine-translated; the original text is authoritative.

The seven structures of the N07 national highway in section 76 (km 7.9 – 27.0) between Frauenfeld and Engwilen were put into service between 1972 and 1992. They comprise three overpasses (UEF Schaffhauserstrasse, UEF Militärstrasse, UEF Bahnhofstrasse) as well as two pairs of bridges over the Thur (Müllheim) and the Engwiler Tobel (Wäldi).

Between 1995 and 2015, partial repairs were carried out on individual structures (expansion joints, waterproofing, concrete repairs, scour protection). A comprehensive, coordinated repair like the one planned has not yet taken place.

Substantial damage was found on the seven affected structures during the 2023 main inspection and subsequent special inspections (2025/2026).

Structural safety is not currently under acute threat; the damage primarily affects durability, drainage, and expansion joints. Without prompt repair, progressive damage to the concrete components (chloride ingress, corrosion) and further restriction of operational safety are to be expected.

The available archived basics (logbooks, HI reports 2023, inspection reports, object agreements) are available (will be sent to the PV after procurement), but must be summarized and evaluated by the PV for further processing. In particular, the repair documents from 1995 (Thur bridges) and 1995/2010 (Militärstrasse) must be checked regarding measures carried out vs. omitted.

The detailed project perimeters/project contents, etc., can be found in the project compendium.

The procurement comprises the engineering service for the construction project author for the ASTRA phases:

- Measures concept+ (MK+)

- Measures project (MP)

- Tendering, tender comparison, award application

- Documents for execution

- Construction

- Commissioning, completion

A maintenance concept (EK) for engineering services is not procured; EK services that are necessary for the MK+ must be provided within the MK+.

Furthermore, part of this procurement is:

- Local construction management including CBL (which is however described in a separate specifications document)

The main project objectives are as follows:

· Preservation of the load-bearing capacity and durability of all seven structures in section N07/76 (km 7.9-27.0) through targeted repair of damaged components (expansion joints, drainage, concrete surfaces, bridge ends, edge curbs)

· Ensure operational safety: Prevention of progressive damage (chloride ingress, corrosion of reinforcement/prestressed steel, concrete spalling) and securing of traffic management without load restrictions

Coordinated, efficient execution: Bundling of 14 expansion joint replacements and accompanying concrete repairs into · a single overall contract for the optimal use of personnel, equipment, and closure windows (goal: end of construction at the end of 2029)

o Award strategy, in one or multiple lots, to be determined in the MP

· Interface management with third parties: Early coordination with Canton Thurgau (UEF Schaffhauserstrasse, UEF Bahnhofstrasse, Thur bridges) and City of Frauenfeld (UEF Militärstrasse) for combined surfacing replacement/waterproofing closures and traffic management, if applicable coupling of further measures on the part of the canton/municipality

· Cost and schedule reliability: Adherence to the cost framework and the schedule

· Minimization of traffic disruptions: Keeping closures as short as possible, staged lane reduction, night closures, and flyover testing at the Thur and Engwiler Tobel bridges

Scope of services construction PV:

1. Determination of basics: Depending on the structure, varying amounts of existing documents may be available. The available documents must be procured from the archive by the PV. If documents relevant to the project planning are missing, supplementary on-site determinations of basics must be carried out if necessary.

2. Clarify ownership/maintenance boundaries & update object agreements: no object agreement in KUBA for TG_769; check existing agreements (TG_713, TG_719, TG_743-/+, TG_752) for up-to-dateness, contractually secure interfaces (edge finishes, drainage, marking, lighting)

Environmental coordination Thur bridges: Consultation with FU environment according to measures concept 1. (repair areas above bank area, not directly above river)

2. Overall traffic management concept: Staged lane reduction, night closures, flyover deployment testing, closure list comparison, coordination with territorial unit/traffic service – critical path for construction period 2029

3. Proposals for involving additional specialist planners if necessary

Superordinate coordination:

A BHU is not intended for this project. The project planning takes place within the framework of the PV, possibly FPs and the client. Coordination with other participants (FU, Canton Thurgau, Municipality of Frauenfeld, Municipality of Hüttlingen, Municipality of Müllheim, Municipality of Wäldi, territorial unit, KaPo, etc.) is required and must be initiated and carried out under the lead management of the construction PV.

The superordinate coordination of the other FPs with the construction PV is the responsibility of the construction PV. The latter must assume lead management and coordinate deadlines, submissions, or the like from the FPs.

Dates

  • Questions until: 10.12.2026
  • Submission deadline: 12.01.2027, 23:59
  • Opening of bids: 15.01.2027

Suitability criteria

  1. EK 1

    Technical capability (company reference)

    Proof: For the tenderer: One reference project regarding completed work with comparable complexity and from the same specialist area. For the proof of all tendered phases, a second reference project can be provided if necessary. If a second reference project is specified, it will be considered exclusively for the proof of the project phase missing in the first specified reference project.

  2. EK 2

    Qualification of the key person project manager construction project author (PL PV Bau)

    Proof: For the tenderer: One reference project regarding completed work with comparable complexity and from the same specialist area in an equivalent function or deputy. For the proof of all tendered phases, a second reference project can be provided if necessary. If a second reference project is specified, it will be considered exclusively for the proof of the project phase missing in the first specified reference project. The reference should essentially show the main task areas, the function, and the experience. In addition, a CV of the key person must be enclosed with the bid.

  3. EK 3

    Proof of availability of the key persons

    Proof: Proof that availability is given for the next two years. Detailed listing and presentation of the time workload on the other projects. Required minimum availability: PL PV Bau 15% Deputy PL PV Bau 20% CBL Bau 20% (from Q1/2028)

  4. EK 4

    Proof of economic and financial capability

    Proof: Annual turnover > double the annual turnover of the contract

  5. EC 5

    Proof of the performance share of subcontractors / subplanners

    Proof: Proof that a maximum of 50% of the services are provided by subcontractors (detailed list of any subcontractors planned, including their share of services). Characteristic services are defined as those services to be provided by the key personnel in accordance with the Award Criteria (Project Manager Project Author Construction, Dep. Project Manager Project Author Construction). The key personnel must compulsorily be provided by the main tenderer.

Award criteria

  1. AC 1 Quality of the tenderer · Weighting 40 %

    The evaluation of the three key personnel (Project Manager Project Author Construction, Dep. Project Manager Project Author Construction, Chief Construction Manager Construction) is based on the reference projects as well as the CVs, with the main focus being on the reference projects. Qualification of key personnel regarding the requirements in the project: - Completed works - Comparable complexity - Same specialist areas processed AC1.1 Project Manager Project Author Construction (PM PA Const) Weighting: 20% Description: For the tenderer: One reference project regarding completed work with comparable complexity and from the same specialist area in an equivalent function or deputy. For the proof of all tendered phases, a second reference project can be provided if necessary. If a second reference project is specified, it will be considered exclusively for the proof of the project phase missing in the first specified reference project. The reference should essentially show the main task areas, the function, and the experience. In addition, a CV of the key person must be enclosed with the bid. AC1.2 Dep. Project Manager Project Author Construction (Dep. PM PA Const) Weighting: 10% Description: For the tenderer: One reference project regarding completed work with comparable complexity and from the same specialist area in an equivalent function or deputy. For the proof of all tendered phases, a second reference project can be provided if necessary. If a second reference project is specified, it will be considered exclusively for the proof of the project phase missing in the first specified reference project. The reference should essentially demonstrate the main task areas, the function, and the experience. In addition, a CV of the key person must be enclosed with the tender. AC1.3 Chief Construction Manager Construction (CCM Const) Weighting: 10% Description: For the tenderer: One reference project on completed works with comparable complexity from the same specialist area as chief construction manager or dep. chief construction manager. The reference should essentially show the main task areas, the function, and the experience. In addition, a CV of the key person must be enclosed with the bid.

  2. AC 2 Quality of the tender · Weighting 30 %

    The quality of the tender is evaluated using the three sub-award criteria 'Task analysis', 'Procedure proposal with project organization', and 'Plausibility of the tender'. AC2.1 Task analysis Weighting: 10% Description: The task analysis must address the following topics: a) Initial situation and objective b) Special technical challenges of the project c) Special organizational challenges of the project d) Assessment of the fee hours and distribution specified by the client (fee table) AC2.2 Procedure proposal with project organization Weighting: 10% Description: The procedure proposal must address the following topics: a) Structured procedure plan with the main focuses in project processing b) Special risks from the perspective of the tenderer and measures to manage these risks c) Project-related organization chart and detailed program phase MK+ up to commissioning with the involvement of specialists and third parties, including information on planned employees per function and coordination of project participants AC2.3 Plausibility of the tender Weighting: 10% Description: The plausibility of the tender is evaluated as follows: The plausibility check of the tender examines whether the individual tender components are coordinated with one another and comprehensible. It is checked whether the organization chart matches the deployed personnel and the hour allocation and whether it coincides with the schedule. Furthermore, it is also checked whether the hour allocation to the individual functions (e.g. PM hours, engineering hours, draftsman hours, etc.) is plausible.

  3. AC 3 Price · Weighting 30 %

    Price