Projects
Planned projects before they are put out to tender: large alpine PV plants with their permit status, transmission lines and rail expansions from the federal sectoral plans, building projects of the City of Zurich under construction, construction and planning credits of the parliaments, neighbourhood plans and urban projects in Geneva, planned public purchases in the French border region and at the SBB, SBB rail projects, Swissgrid grid projects, wastewater plants planning or building a micropollutant stage, the investment plans of Basel-Stadt and the City of Geneva, and the measures of the federal rail expansion and agglomeration programmes.
A project is not a tender. The clients decide whether, when and in which lots contracts are awarded; the tenders follow later, mostly on simap.ch.
Large private and semi-public buyers award many contracts by invitation only. Where to register as a supplier: Supplier portals
- Credit in parliamentStatus unknownFribourg
Crédit d’ouvrage pour la requalification de la place du Petit-Saint-Jean, de la rue de la Samaritaine et de la rue d’Or ainsi que pour l’assainissement du pont du Milieu
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownFribourg
Crédit d’étude pour l’assainissement, la rénovation et la mise aux normes des bâtiments B1, B2 et C du complexe scolaire du Jura
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentDealt with by parliamentTicino
La richiesta di un credito di fr. 4'200'000.- per la realizzazione del nuovo pontile e del molo frangiflutti al porto della foce del Cassarate
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentDealt with by parliamentZurich
Planungskredit Gesamtsanierung und Erweiterung Schulhaus Guldisloo
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownGeneva
Ouvrant des crédits d'étude et d'investissement pour la construction de l'école de commerce de Frontenex
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownGeneva
Ouvrant un crédit d'études et d'investissement de 42 500 000 francs en vue de la construction de 7 écoles de pédagogie spécialisée (ECPS) sur les communes de Vernier, d'Onex et du Grand-Saconnex
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownZug
Tiefbau: Anlagen, Plätze, Gewässer; Instandsetzung öffentliche WC-Anlagen; Objektkredit (Teilkredit)
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownZug
Immobilien: Hofstrasse 5/7/9 (Zurlaubenhof): Sanierung Rosenlaube, Natursteinmauern und "Schnapshüsli"; Zahlungskredit
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentDealt with by parliamentSolothurn
Mehrjahresplanung ab 2025 «Strassenbau»; Rechenschaftsbericht über die Projekte; Verpflichtungskredit für Kleinprojekte ab 2025
Business on OpenParlData.chBusiness on the parliament's site
- Investment planCredit approvedBasel-Stadt
Winterdienstaggregate
Amount in the plan: CHF 1’200’000
Source: Canton of Basel-Stadt, Finance Department, Budgetbericht 2026, Kap. 5.1.3 Investitionsübersichtsliste, S. 338, as of 23.10.2025
- Credit in parliamentDealt with by parliamentTicino
La richiesta di un credito di fr. 1’770'000.-- per il potenziamento e la sistemazione della rete acqua potabile a Lugano Barbengo (Via Figino), per la modifica dell’impianto di trattamento presso la stazione filtri a Bioggio, e per l’esecuzione di una nuova vasca antincendio a tutela e presso il demanio forestale del Cusello, e interventi concomitanti per idranti
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentCredit approvedGeneva
Ouverture de deux crédits d’étude pour un montant total de 2 568 500 francs destinés aux études de réaménagement des espaces publics et de réhabilitation du réseau secondaire d’assainissement des eaux de la Ville de Genève du secteur «James-Fazy / Terreaux-du-Temple»
- Credit in parliamentCredit approvedGeneva
Ouverture de deux crédits pour un montant total de 1 383 000 francs destiné à l’étude d’aménagement de l’avenue de la Jonction et des rues adjacentes et de la mise en conformité et le développement de la mise en séparatif du réseau d’assainissement des eaux pour le périmètre de la pointe de la Jonction
- Credit in parliamentCredit approvedGeneva
Ouverture de deux crédits pour un montant total de 949 200 francs destiné aux études d’aménagement de la place de Saint-François et de ses abords et pour la mise en conformité et la mise en séparatif du réseau d’assainissement des eaux pour le périmètre place de Saint-François / boulevard du Pont-d’Arve
- Credit in parliamentDealt with by parliamentZurich
Verpflichtungskredit in der Höhe von Fr. 5'280'000 für den Bau der Wärmeversorgungsinfrastruktur im Wärmeversorgungsgebiet Seen, für Anpassungen der Wärmeversorgungsinfrastruktur im Quartierwärmeverbund Waser und in der Holzheizzentrale Waser sowie für den Anschluss des Schulhauses Steinacker einschliesslich privater Liegenschaften
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentDealt with by parliamentTicino
Richiesta di un credito di 4’253’000 franchi e un’autorizzazione alla spesa di 8’088’000 franchi per la progettazione e la realizzazione di due opere di mobilità del Programma d’agglomerato del Mendrisiotto di terza generazione (PAM3)
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentStatus unknownZurich
Umbau temp. Asylunterkunft Grünaustrasse, Ausführungskredit
Business on OpenParlData.chBusiness on the parliament's site
- Credit in parliamentCredit approvedGeneva
Ouverture d’un crédit pour un montant total de 886 900 francs destiné à la réalisation d’une passerelle piétonne permettant de relier la rue de Lausanne au parc William-Rappard
- Investment planCredit approvedGeneva
2ème PBTN - Plan biennal transformation numérique
Amount in the plan: CHF 4’520’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 48, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Etude d'aménagement
Amount in the plan: CHF 250’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 42, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Etude d'aménagement
Amount in the plan: CHF 700’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 42, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Etude d'aménagement du "Boulevard Urbain"
Amount in the plan: CHF 1’900’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 42, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Etudes d'aménagements
Amount in the plan: CHF 2’000’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 42, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Etudes d'assainissements des eaux
Amount in the plan: CHF 450’000
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 38, as of Situation au 29.08.2025
- Investment planCredit approvedGeneva
Mission OPC, études
Amount in the plan: CHF 436’700
Source: City of Geneva, 21ème Plan financier d'investissement 2026-2037, Crédits votés, p. 42, as of Situation au 29.08.2025
Quelle: Bundesamt für Energie (BFE), Photovoltaik-Grossanlagen in der Schweiz
The information comes from an external source (BFE – Photovoltaik-Grossanlagen in der Schweiz) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(BFE – Photovoltaik-Grossanlagen in der Schweiz, opens in a new tab)Terms of use(BFE – Photovoltaik-Grossanlagen in der Schweiz, opens in a new tab)
Quelle: Bundesamt für Energie (BFE), Sachplan Übertragungsleitungen (SÜL)
The information comes from an external source (BFE – Sachplan Übertragungsleitungen (SÜL)) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(BFE – Sachplan Übertragungsleitungen (SÜL), opens in a new tab)Terms of use(BFE – Sachplan Übertragungsleitungen (SÜL), opens in a new tab)
Quelle: Bundesamt für Verkehr (BAV), Sachplan Verkehr, Teil Infrastruktur Schiene (SIS)
The information comes from an external source (BAV – Sachplan Verkehr, Teil Infrastruktur Schiene (SIS)) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(BAV – Sachplan Verkehr, Teil Infrastruktur Schiene (SIS), opens in a new tab)Terms of use(BAV – Sachplan Verkehr, Teil Infrastruktur Schiene (SIS), opens in a new tab)
Quelle: Stadt Zürich, Amt für Hochbauten, AHB-Hochbauprojekte in Ausführung OGD
The information comes from an external source (Stadt Zürich – AHB-Hochbauprojekte in Ausführung) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(Stadt Zürich – AHB-Hochbauprojekte in Ausführung, opens in a new tab)Terms of use(Stadt Zürich – AHB-Hochbauprojekte in Ausführung, opens in a new tab)
Source: OpenParlData.ch
Business with construction and planning credits selected by TEXFY; titles, statuses and dates as delivered.
The information comes from an external source (OpenParlData.ch – Bau- und Projektierungskredite der Parlamente) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(OpenParlData.ch – Bau- und Projektierungskredite der Parlamente, opens in a new tab)Terms of use(OpenParlData.ch – Bau- und Projektierungskredite der Parlamente, opens in a new tab)
Quelle: APProch – Projets d'achats publics, Direction des Achats de l'État, über data.gouv.fr, Licence Ouverte 2.0, Stand der Daten 10.11.2026. Geplante Beschaffungen sind unverbindlich und nicht vollständig; keine Ausschreibung.
The information comes from an external source (APProch – Projets d'achats publics (Frankreich)) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(APProch – Projets d'achats publics (Frankreich), opens in a new tab)Terms of use(APProch – Projets d'achats publics (Frankreich), opens in a new tab)
Source : Portail des données SITG (État de Genève), téléchargé et/ou extrait en date du 10.11.2026.
Fields selected and presented by TEXFY (compilation under condition 5.3.2 of the SITG).
Further use of these data is subject to the terms of use of the Portail des données SITG (condition 5.5.1).
The information comes from an external source (SITG Genève – Plans localisés de quartier (adoptés et en procédure)) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(SITG Genève – Plans localisés de quartier (adoptés et en procédure), opens in a new tab)Terms of use(SITG Genève – Plans localisés de quartier (adoptés et en procédure), opens in a new tab)
Source : Portail des données SITG (État de Genève), téléchargé et/ou extrait en date du 10.11.2026.
Fields selected and presented by TEXFY (compilation under condition 5.3.2 of the SITG).
Further use of these data is subject to the terms of use of the Portail des données SITG (condition 5.5.1).
The information comes from an external source (SITG Genève – Projets urbains du plan directeur cantonal) and is not an official publication of this platform. The original publication is authoritative.
Source dataset(SITG Genève – Projets urbains du plan directeur cantonal, opens in a new tab)Terms of use(SITG Genève – Projets urbains du plan directeur cantonal, opens in a new tab)
Quelle: Schweizerische Bundesbahnen SBB, Bahnprojekte und regionale Bauprogramme (company.sbb.ch)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
The information comes from an external source (SBB – Bahnprojekte und regionale Bauprogramme) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(SBB – Bahnprojekte und regionale Bauprogramme, opens in a new tab)Operator's legal notice(SBB – Bahnprojekte und regionale Bauprogramme, opens in a new tab)
Quelle: Schweizerische Bundesbahnen SBB, Geplante Beschaffungen SBB Infrastruktur (Excel-Liste)
Die veröffentlichten Einträge dienen ausschliesslich zu Informationszwecken. Aus der Veröffentlichung entsteht kein Anspruch auf den Rechtsweg oder sonstige rechtliche Ansprüche gegenüber dem Herausgeber.
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
The information comes from an external source (SBB – Geplante Beschaffungen SBB Infrastruktur) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(SBB – Geplante Beschaffungen SBB Infrastruktur, opens in a new tab)Operator's legal notice(SBB – Geplante Beschaffungen SBB Infrastruktur, opens in a new tab)
Quelle: Swissgrid AG, Projektübersicht der Netzprojekte (swissgrid.ch)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
Dates as written on the project page, sorted by kind by TEXFY; Swissgrid states them for an optimal course without court proceedings.
The information comes from an external source (Swissgrid – Netzprojekte (Projektübersicht)) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(Swissgrid – Netzprojekte (Projektübersicht), opens in a new tab)Operator's legal notice(Swissgrid – Netzprojekte (Projektübersicht), opens in a new tab)
Quelle: VSA-Plattform «Verfahrenstechnik Mikroverunreinigungen», Liste der ARA mit MV-Stufe (micropoll.ch)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
The information comes from an external source (VSA-Plattform Mikroverunreinigungen – Liste der ARA mit MV-Stufe) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(VSA-Plattform Mikroverunreinigungen – Liste der ARA mit MV-Stufe, opens in a new tab)Operator's legal notice(VSA-Plattform Mikroverunreinigungen – Liste der ARA mit MV-Stufe, opens in a new tab)
Quelle: Kanton Basel-Stadt, Budgetbericht 2026, Investitionsübersichtsliste (Kap. 5.1.3)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
Only the building and infrastructure part of the list is taken over: urban development and public space infrastructure, public transport, administrative buildings.
Amounts as written in the document (in francs, thousand or million francs); TEXFY converts them to francs.
The information comes from an external source (Kanton Basel-Stadt – Investitionsübersichtsliste (Budgetbericht)) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(Kanton Basel-Stadt – Investitionsübersichtsliste (Budgetbericht), opens in a new tab)Operator's legal notice(Kanton Basel-Stadt – Investitionsübersichtsliste (Budgetbericht), opens in a new tab)
Source : Ville de Genève, 21ème Plan financier d'investissement 2026-2037
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
The lists of voted and submitted credits and of the plan's active projects are taken over, without the revenue.
The information comes from an external source (Ville de Genève – Plan financier d'investissement (PFI)) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(Ville de Genève – Plan financier d'investissement (PFI), opens in a new tab)Operator's legal notice(Ville de Genève – Plan financier d'investissement (PFI), opens in a new tab)
Quelle: Bundesamt für Verkehr BAV, Kennzahlen zu Standbericht Eisenbahnausbauprogramme (Datenbeilage zum Standbericht 2025)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
Measures as of the report's reference date; TEXFY does not show measures marked as suspended (“sistiert”) or finished (“beendet”) as projects.
Amounts as written in the document (in francs, thousand or million francs); TEXFY converts them to francs.
The information comes from an external source (BAV – Kennzahlen zum Standbericht der Bahnausbauprogramme) and is not an official publication of this platform. The original publication is authoritative.
Operator's page(BAV – Kennzahlen zum Standbericht der Bahnausbauprogramme, opens in a new tab)Operator's legal notice(BAV – Kennzahlen zum Standbericht der Bahnausbauprogramme, opens in a new tab)
Quelle: Bundesamt für Raumentwicklung ARE, Factsheets «Mitfinanzierte Agglomerationsprogramme der 5. Generation» (Vernehmlassung Verkehr ’45)
Only facts per project are taken over (name, place, kind, phase, dates, amounts), with a link to the original; TEXFY does not take over the source's texts, files or layout. Only the original is binding.
State of the consultation “Transport ’45” of 19.06.2026: Parliament decides on the federal contributions. Measures of priority B and C are not co-financed by the Confederation in this generation.
Amounts as written in the document (in francs, thousand or million francs); TEXFY converts them to francs.