Après analyse complète des offres reçues, conformément aux exigences du dossier d'appel d'offres, l'offre a été jugée la plus avantageuse conformément à la grille d'évaluation.
- Construction and installation
- BKP 112 Deconstruction
- BKP 114 Earth movement
- +5
Collège de la Gouvernière Assainissement et Mise en Conformité du Bâti et Aménagements des Alentours - Travaux de l'Entreprise de Maconnerie et Genie Civil
- Location
- Canton NE
- Procuring office
- Commune de Lignières (OS+ACE Consortium d'architectes)
Awarded
Awarded to
- S. Facchinetti S.A., NeuchâtelCHF 1’338’013.80
What is being procured?
Scope of work
Selon descriptif détaillé présent dans le dossier.
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 112 – Deconstruction
- BKP 114 – Earth movement
- BKP 211 – Builder's work
- eBKP-H B05.02 – Deconstruction of non-contaminated works
- eBKP-H B06.01 – Non-contaminated spoil
- eBKP-H C01 – Foundations, ground slabs
- eBKP-H C02 – Structural walls
- OAG 1.2.2 – General education school
- CPV
- CPV 45262300 – Concrete work
- CPV 45111100 – Demolition work
- CPV 45112500 – Earthmoving work
- CPV 45262500 – Masonry and bricklaying work
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 26373
- Publication number
- 26373-02
- Covered by international agreements
- No
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.