Tender, extract
Overall Project St. Anna-Strasse - Bellerivehöhe - Schlösslihalde
- Contracting authority
- Stadt Luzern, Umwelt- und Mobilitätsdirektion, Tiefbauamt
- Place
- Canton LU
- Submission deadline
- 24.11.2026, 12:00
- Published
- 15.10.2026
- Procedure
- Open procedure
- Type
- Construction and installation
- Project number
- 44674
- CPV code
- 45000000 Construction work
- Languages of the bid
- German
Description
The overall project has been divided into three sub-projects, primarily for approval and permitting purposes. All three sub-projects have been approved and will be implemented jointly as a single overall project.
Part 1:
Section: Schädrütistrasse / Schlösslihalde Intersection to and including Schlösslirain Junction
The rehabilitation section has a length of approximately 490 m. The bus stops Schlösslihalde and Schlösslirain are located within this section and will be upgraded to provide barrier-free access in compliance with accessibility requirements.
To meet the City of Lucerne's required bus stop standards, some platform edges will be repositioned, raised, and equipped with specially shaped kerbstones (Lucerne special kerb design). Traffic refuge islands will also be reconstructed at optimized locations.
At the Schlösslirain junction, the intersection geometry will be improved and a standard-compliant pedestrian sidewalk crossing will be constructed. The rear edges of the sidewalks will remain unchanged.
The carriageway width on straight sections will be approximately 9.10 m. The sidewalks on both sides will each provide a width of approximately 2.0 m. To maintain the existing overall road width, any additional space required in constrained areas will be taken equally from both sidewalks.
The rehabilitation works include complete replacement of the pavement structure. Based on borehole cores and site investigations, the existing foundation material is in good condition and only requires recompaction.
Part 2:
Section: Beyond the Schlösslirain Junction to Before the Rigistrasse Junction
The rehabilitation section has a length of approximately 470 m.
The Leumatt bus stop, including the turning loop and adjoining carriageway/sidewalk area (approximately 130 m in total), has already been reconstructed. No additional bus stops are located within this section.
One traffic refuge island will be modified. The rear edges of the sidewalks will remain unchanged. The carriageway width on straight sections will be 9.10 m, and the sidewalks on both sides will each be approximately 2.0 m wide.
To preserve the existing overall road width, any additional space required in constrained areas will be taken equally from both sidewalks.
The rehabilitation works include full pavement replacement. Based on borehole cores and subsurface investigations, the foundation material is in good condition and only requires recompaction.
Part 3:
Section: Rigistrasse Junction to Gundoldingenstrasse Junction
The rehabilitation section has a length of approximately 620 m.
The bus stops Rigistrasse, Lützelmattstrasse, and Klinik St. Anna will be upgraded to provide barrier-free access.
To comply with the City of Lucerne's bus stop standards, selected platform edges will be repositioned, raised, and equipped with specially shaped kerbstones (Lucerne special kerb design). Traffic refuge islands will also be rebuilt at optimized locations.
At the Rigistrasse junction and the Klinik St. Anna access junction, the intersection geometry will be improved and standard-compliant pedestrian sidewalk crossings will be constructed.
The rear edges of the sidewalks will remain unchanged. The carriageway width on straight sections will be 8.10 m, while sidewalks on both sides will each be approximately 2.0 m wide.
To maintain the existing road width, any additional space required in constrained areas will be taken equally from both sidewalks.
The rehabilitation works include complete pavement replacement. Based on borehole cores and site investigations, the foundation material is in good condition and requires only recompaction.
At the same time, St. Anna Hospital (ANNAplus) is undergoing redevelopment. The works must therefore be coordinated with the hospital construction activities. Within the hospital area, the installation of the water mains will be advanced to autumn 2026.
The road construction works covered by this contract will be carried out within the scope of the present project but as separate and independently scheduled construction phases, currently anticipated for 2029 (see Construction Schedule, Phases 31/32) or at another date depending on the progress of the hospital redevelopment project.
Civil Engineering Works
- Pavement construction including foundation layers and kerb installations.
- Construction of 2 concrete bus stops (barrier-free and disability-compliant).
- Construction of 8 bus stops with concrete kerb strips (barrier-free and disability-compliant).
- Construction of 2 passenger shelters (foundations by others, shelter structures supplied by third parties) and raising of 1 existing passenger shelter.
- Intersection improvements and pedestrian sidewalk crossings.
- Streetscape redesign and reallocation of traffic areas (new kerb alignments).
- Construction and modification of the road drainage system, including connections to the main sewer.
- Water supply works: replacement of the existing transmission main and construction/modification of distribution mains (including rehabilitation of service connection lines).
- Construction and rehabilitation of gas pipeline sections requiring renewal.
- Construction and rehabilitation of wastewater drainage sections requiring renewal.
- Modification of electrical utility corridors (including cable chambers/manholes) and street lighting.
- Culvert structure for the Gerlisbergbach stream.
Constraints and Restrictions
- Various project-specific boundary conditions and construction constraints must be taken into account (refer to the tender documents).
- All works shall be carried out while maintaining traffic flow, in particular public bus services and emergency services.
- The works shall be executed in stages and, where necessary, in smaller sub-stages, taking into consideration all project constraints and requirements. Within each main construction stage, the works shall be implemented through three parallel construction phases.
- Available working space is very limited in certain sections.
- Noise emissions shall be kept to a minimum.
- Safe access to residential properties, business entrances and exits, adjacent construction sites, and other affected areas shall be maintained at all times for all road users.
- St. Anna Hospital shall remain fully accessible day and night at all times for emergency vehicles, hospital staff, patients, and visitors without restriction.
- It shall be ensured at all times that adequate and safe conditions are maintained for residents, property access, pedestrians, cyclists, public transport, private motorised traffic, and all other road users. Simultaneously, disruptions and inconveniences to traffic and local stakeholders shall be kept to an absolute minimum.
Schedule
- Construction works shall commence on 5 April 2027.
- The works shall be executed in several main construction stages, each consisting of multiple parallel construction phases.
- Further details regarding the project schedule and key dates can be found in the tender documentation (refer to Section 2.11).
Dates
- Questions until: 01.11.2026
- Submission deadline: 24.11.2026, 12:00
- Opening of bids: 24.11.2026, 14:00
Suitability criteria
EK 1
Fachkompetenz und Erfahrung Unternehmung (Referenzobjekte)
Proof: Zwei projektbezogene, vergleichbare Referenzobjekte im Strassen- und Werkleitungsbau mit Bausumme jeweils grösser Fr. 2.0 Mio. innerhalb der letzten 10 Jahre, in welchen die nachfolgenden, weiteren Bedingungen nachgewiesen werden. Diese weiteren Bedingungen müssen nicht zwingend bei jedem Referenzobjekt erfüllt sein. Der Nachweis kann insgesamt über beide Referenzobjekte erbracht werden: Erstellung hindernisfreie Bushaltestelle, Bauen unter Verkehr auf verkehrsorientierten Strassen innerorts.
EK 2
Leistungsfähigkeit
Proof: Der Anbieter (Einzelanbieter für sich, ARGE als Gruppe) muss den Nachweis erbringen, die ausgeschriebenen Arbeiten im vorgesehenen Terminrahmen ausführen zu können. Die angebotene Bausumme darf maximal 30 % des durchschnittlichen Jahresumsatzes der letzten 3 Jahre der Einzelfirma bzw. der Bietergemeinschaft/ARGE als Gruppe betragen. Dasselbe gilt für technisch und terminlich relevante vorgesehene Subunternehmer und ist ebenfalls nachzuweisen. Die Jahresumsätze aller 3 Jahre sind offen darzulegen.
EK 3
Selbstdeklaration
Proof: Selbstdeklaration gemäss separatem Formular und Selbstdeklaration SECO Ukraine.
EK 4
Haftpflichtversicherung
Proof: Nachweis Haftpflichtversicherung grösser 10 Mio.
Award criteria
ZK 1 · Weighting 45 %
Angebotspreis Die Bewertung des Preises erfolgt nach folgender Bewertungsmethode: Das Angebot mit dem tiefsten Preis erhält die maximale Punktzahl 5. Angebote, die 50% oder mehr vom tiefsten Preis abweichen, erhalten die Punktzahl 0. Dazwischen werden die Punktzahlen (auf eine Kommastelle gerundet) linear vergeben und mit der Gewichtung multipliziert.
ZK 2 · Weighting 25 %
Erfahrung / Fachliche Kompetenz der Schlüsselpersonen Schlüsselpersonen sind: Ein Bauführer und ein Hauptpolier Der Nachweis ist für jede einzelne Schlüsselperson (gemäss dem Dokument Unternehmerangaben in den Ausschreibungsunterlagen) zu erbringen. Es wird das Mittel der einzelnen Schlüsselpersonen-Kategorie gemäss Angaben und Datenblätter der einzelnen Personen aus den Eignungskriterien ermittelt. Der Unternehmer bestätigt mit der Eingabe des Angebots, dass die Projektleitung bemächtigt wird, allfällige Referenzen über die einzelnen Schlüsselpersonen einzuholen
ZK 3 · Weighting 30 %
Bauprogramm / Bauzeitoptimierung Zu berücksichtigen und aufzuzeigen sind alle Bauarbeiten. Aufzeigen der Bauabläufe in Form eines Balkendiagramms inkl. Nachweis für die Einhaltung der Vorgabetermine der Bauherrschaft. Aufzeigen des Personal- und Maschineneinsatzes sowie des Installations- und Logistikkonzeptes im Zusammenhang mit den Bauabläufen. Zusätzlich soll auf die Besonderheit der vorliegenden Ausführung in Hauptetappen mit jeweils drei gleichzeitig laufenden Bauphasen eingegangen werden. Gewertet werden insbesondere folgende Bewertungselemente: Einreichung eines nachvollziehbaren und plausiblen Bauprogramms mit einer allfälligen Bauzeiteinsparung gegenüber des ausgeschriebenen Endtermins der Hauptarbeiten am 08.09.2028 (Amtsvorschlag exkl. Bauphasen 31/32 und Deckbelagsarbeiten) ergeben höhere Punktzahlen. Detailliertes Bauprogramm (Balkendiagramm): Plausibilität, Ressourceneinsatz (Ausführung in drei parallel arbeitenden Gruppen ist aufzuzeigen), Korrektheit und Vollständigkeit der Bauabläufe inkl. Aufzeigen Anteil Zeit Dritte (z.B. Rohrleitungsbau ewl Wasser etc.), Erkennen des kritischen Weges, Aufzeigen von Reserven, Nachweis für die Einhaltung der Vorgabetermine der Bauherrschaft. Aufzeigen des Personal- und Maschineneinsatzes sowie des Installations- und Logistikkonzeptes im Zusammenhang mit den Bauabläufen. Eine Besonderheit des vorliegenden Projekts besteht darin, dass die Ausführung aus zehn Hauptetappen besteht mit jeweils in einer Hauptetappe drei parallellaufenden Bauphasen. Eine Hauptetappe gilt als abgeschlossen, wenn sämtliche darin enthaltenen Bauphasen ausgeführt sind. Erst anschliessend kann die Phasenumstellung auf die nächste Hauptetappe erfolgen. Der Anbieter hat aufzuzeigen, wie mit den unterschiedlichen Bauvolumen der gleichzeitig auszuführenden Bauphasen einer Hauptetappe umgegangen wird. Dabei sind mögliche Optimierungspotenziale hinsichtlich des Bauablaufs, des Ressourceneinsatzes und der eingesetzten Geräte aufzuzeigen. Der Anbieter hat den Umgang und die Auswirkungen (auf Bauzeit/Bauablauf) einer allfälligen Reduktion der pro Hauptetappe parallel auszuführenden Bauphasen von drei auf zwei Phasen aufzuzeigen bzw. zu beschreiben. Bewertung: Vollständigkeit, Detaillierungsgrad, Nachvollziehbarkeit, Anwendung auf das spezifische Projekt.
Submission
- Online via simap.ch
Links
- This tender in TEXFY: https://www.texfy.ch/en/ausschreibungen/ef57841d-31d2-4b51-94bb-8801261b8abc
- Official publication: https://www.simap.ch/en/project-detail/0d2a6f84-81c0-412e-85b8-9b9a384d7185