All tenders
Open · 37 days left
  • Construction and installation
  • BKP 213 Prefabricated steel construction

Renovation/Conversion of the CID in Malley / Metal construction

Published in French. Sign in and TEXFY shows the texts in English. Sign in

Go to the official tender(simap.ch, opens in a new tab)

At a glance

Deadline
18.12.2026, 11:0037 days left
Type
Construction and installation
Procedure
Open procedure
Award weighting
In the documents
Eligibility
In the documents

Is a bid worth it?

With a free profile, TEXFY checks this tender against your services and cantons: a relevance grade from A to E and a recommendation with reasons.

Start for free

TEXFY assessment: Risks and notes

  • Mandatory site visit: check the dateImportant

    According to the publication, attending is mandatory; date and place are in the note. Check there whether the visit is still ahead: missing it risks exclusion.

    Une visite obligatoire du Centre intercommunal de gestion des déchets (CID) de Malley aura lieu le 10 novembre 2026 à 13h00 uniquement pour permettre aux soumissionnaires de mieux comprendre les travaux à … From «Site visit»

  • Bid languageNote

    The bid must be in French.

    From «Bid languages»

  • Subcontracting limitedGood to know

    The publication limits subcontracting, for example by share or by requiring consent.

    Sous-traitance limitée à 30% maximum du montant du marché From «Subcontractors»

1 more note
  • No variantsGood to know

    Only the requested bid counts; your own alternative solutions are not allowed.

    From «Variants»

TEXFY assessment: by fixed rules, no AI. Everything else comes from the publication; in another language it is machine-translated.

Checked against simap: 10.11.2026, 18:02

What is being procured?

Scope of work

Construction d’un couvert en métal au-dessus de la future station de lavage. (Liste L1)

Renforcement des poutres métalliques principales de la toiture du bâtiment afin de pouvoir y ajouter par la suite des panneaux solaires. (Liste L2)

Fourniture et pose de diverses pièces métalliques selon les besoins du chantier. (Liste L3)

Key facts, codes and options

Type of contract
Construction and installation
Type of construction
Building construction
Construction service
Design and execution
Procedure
Open procedure
Trades
  • BKP 213 – Prefabricated steel construction
  • OAG 1.3.1 – Heavy-industrial building
CPV
  • CPV 45000000 – Construction workCPV general: general code without a field
Options
Not provided for
Variants
Not admitted
Partial offers
Not admitted

TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.

Dates

Published
03.11.2026
Questions untilnext
17.11.2026

à 11h

Submission deadline
18.12.2026, 11:00
Bid valid
until 18.06.2028
Contract
10.02.2027 to 31.12.2028

Site visit

Mandatory according to the publication
Note of the contracting authority (date, time and place as published)

Une visite obligatoire du Centre intercommunal de gestion des déchets (CID) de Malley aura lieu le 10 novembre 2026 à 13h00 uniquement pour permettre aux soumissionnaires de mieux comprendre les travaux à réaliser décrits dans la série de prix. Il ne sera répondu à aucune question sur place.

Submission & documents

The tender names 2 routes. We submit nothing for you.

  • Online via simap.ch

    Once submitted, the bid can no longer be changed on simap.ch.

    Source: simap data

  • By post or delivery in person

    Ville de Lausanne - Service de la propreté urbaineRue des Terreaux 331003 Lausanne

    The information in the tender and the tender documents is authoritative. Check in particular whether the postmark or receipt counts.

    Source: simap data

Tender documents
Documents on simap.ch (after signing in)
Languages of the bid
French
Language of the documents
French
Cost of the documents
Free of charge
Questions to the contracting authority
Through the question forum on simap.ch (registration as a bidder required). Go to the official tender (simap.ch, opens in a new tab)TEXFY sends no questions. The deadlines of the question rounds are under “Dates”.

Participation & award

In the documents according to the source: Content only in the tender documentsIn the tender documents: Suitability criteria, Award criteria, Conditions of participation, Documents to submit.

Conditions

Rules for the bid and the contract, for example whether consortia or subcontractors are allowed and how payment works.

4 conditions
Bidding consortia
Allowed
Subcontractors
Allowed

Sous-traitance limitée à 30% maximum du montant du marché

Contract extension
Not provided for
Dialogue
Not provided for

The glossary explains terms such as eligibility criteria, self-declaration or reference. To the glossary

Official source

Go to the official tender(simap.ch, opens in a new tab)
simap project number
46214
Publication number
46214-01
Covered by international agreements
Yes
Notice of legal remedies
Show

Le présent appel d’offres peut faire l’objet d’un recours à la Cour de droit administratif et public du Tribunal cantonal, route du Signal 8, 1014 Lausanne, dans les vingt jours dès sa notification par publication ; le recours doit être signé et indiquer les conclusions et ses motifs. La décision attaquée est jointe au recours.

Checked against simap: 10.11.2026, 18:02

Export

This is not an official publication. Only the data published on the platform www.simap.ch is authoritative. Dies ist keine amtliche Veröffentlichung. Massgebend sind die auf der Plattform www.simap.ch veröffentlichten Daten. Anyone who reuses this data complies with the conditions of simap.ch: terms, section 6.

Contract awards in Vaud: monthly reports
Report a data error

Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.

Kind of error

Please do not write personal data into it. If you are signed in, we store the report with your account.