- Construction and installation
MP-160010 N01/42, 46 ZH-Nord interchange – ZH-Ost interchange – Brüttisellen interchange
- Procuring office
- Bundesamt für Strassen ASTRA - Filiale Winterthur
At a glance
- 28.01.2027, 23:5970 days left
- Open procedure
- 01.02.2028 to 31.12.2031
Is a bid worth it?
With a free profile, TEXFY checks this tender against your services and cantons: a relevance grade from A to E and a recommendation with reasons.
TEXFY assessment: Risks and notes
Bid languageNote
The bid must be in German.
References requiredNote
For eligibility you need comparable reference projects. Check number, age and size.
Securities per contractGood to know
Whether a surety or guarantee is needed is set out in the contract or the documents. Check there.
2 more notes
Subcontracting limitedGood to know
The publication limits subcontracting, for example by share or by requiring consent.
Paper onlyGood to know
Submission by post or in person. Allow for delivery and check whether the postmark or receipt counts.
What is being procured?
Scope of work
The project N01/42, 46 Verzw. ZH-Nord – Verzw. ZH-Ost – Verzw. Brüttisellen (short form: PZO) provides for the reduction of existing capacity bottlenecks in the area of the Brüttisellen junction up to the Zürich-Ost junction and the improvement of traffic flow. For this purpose, the implementation of a permanent hard shoulder use (PUN) and various structural measures on the route and engineering structures are planned. Further project components include noise remediation (new construction of 5 LSW, replacement construction of 1 LSW) as well as road wastewater treatment (new construction of 2 SABA).
The present mandate of the master builder for the main steel construction works (construction package 3) essentially comprises the following works:
- Production, assembly and delivery of 20 new signal gantries required for the safety-related signalling of the various operating states within the project perimeter.
- Widening of 3 existing signal gantries
- Demolition of 4 existing signal gantries
- Reinforcement of 1 existing signal gantry
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Civil engineering
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- Not evident from the available publication data.
- CPV
- CPV 45223210 – Structural steelworks
- Options
- Not provided for
- Variants
- Admitted
Lump-sum and global tenders and/or tenders with a time-rate tariff are excluded. The official variant must be submitted in full in any case. No project variants are accepted. In particular, a project variant is considered to be a variant in which the result of the executed structure is not identical to the detailed project or measure project, including the building materials used. Technical variants are permitted in compliance with the conditions pursuant to Special Construction Provisions (BBB Bau Ziff. 260 ff.).
- Partial offers
- Not admitted
Tenders must be submitted fully completed. Amendments to the tender text are not permitted. Partial tenders are invalid and will be excluded from the application.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Dates
- Published
- 19.11.2026
- Questions untilnext
- 18.12.2026
Questions must be submitted in German via www.simap.ch in the "Forum". They will be answered identically to all recipients of the tender documents by 12/01/2027 in the "Forum" at www.simap.ch. Questions arriving after 18/12/2026 will no longer be answered.
- Submission deadline
- 28.01.2027, 23:59
- Opening of bids
- 04.02.2027, not public
- Bid valid
- 180 days after the deadline
180 days from the deadline for receipt of tenders.
- Contract
- 01.02.2028 to 31.12.2031
- Execution
- 01.02.2028 to 30.11.2030
Site visit
No site visit will take place.
Submission & documents
By post or delivery in person
Bundesamt für Strassen ASTRA - Filiale WinterthurGrüzefeldstrasse 418404 WinterthurSource: simap data
Special submission route
Two (2) copies of the tender (tender documents) in paper form with original signatures must be submitted. In addition, the tender must be submitted in electronic form (e.g. on a USB stick). It must consist of a single PDF file comprising the entire physical tender. Only files in special formats are exempt from this rule and may be submitted separately (in addition to the PDF file).
Personal delivery:
Delivery must be made at the latest by the submission date mentioned above during the opening hours of the lodge (07:45 - 11:45 and 13:15 - 16:45 (Friday until 16:00)) against issuance of a receipt.
Submission by mail:
A-Post or PostPac Priority (postmark date of a Swiss or state-recognized foreign post office; company frankings are not considered postmarks). In any case, the tenderer(s) must ensure proof of timely submission of the tender. Late tenders will no longer be considered. The endorsement "Nicht öffnen - Offertunterlagen" must be clearly affixed to the envelope alongside the project designation.
Handover to a diplomatic or consular representation of Switzerland:
Foreign tenderers may hand over their tender to a diplomatic or consular representation of Switzerland in their country at the latest by the submission date mentioned above, during opening hours, against issuance of a receipt.
In this case, tenderers are obliged to send the receipt to the procurement office by e-mail before the submission deadline.
Tenders submitted by e-mail or fax will not be considered!
Source: simap data
- Documents on simap.ch (after signing in)
- German
- German
- Free of charge
- Through the question forum on simap.ch (registration as a bidder required).
Participation & award
Participation & suitability
4 eligibility criteria
EK 1
TEXFY assessment: What this means: Experience – whether you have carried out comparable contracts, shown with references.
Technical capacity
For the tenderer: 1 reference project regarding completed works with comparable complexity and from the same specialist area.
EK 2
TEXFY assessment: What this means: Finances – whether your company is financially sound and adequately insured, e.g. with a debt enforcement extract and proof of insurance.
Economic / financial capacity
For the tenderer: Proof of turnover for the years 2023-2025; the annual turnover of the tenderer must be at least twice the annual turnover of the contract. Joint ventures may only add up the annual turnover of the respective companies in proportion to their participation in the joint venture.
EK 3
TEXFY assessment: What this means: Personnel – how qualified and experienced the people carrying out the contract are, such as the project manager.
Experience of key person "Technical Manager"
For the key person "Technical Manager": 1 reference object regarding completed works in an equivalent function or deputy function with comparable complexity and from the same specialist area.
EK 4
TEXFY assessment: What this means: Subcontracting – how much of the work you may pass on to other companies.
Share of performance by subcontractors
For the tenderer: Proof that a maximum of 50% of the services are provided by subcontractors.
All economically and technically capable companies that also provide the following suitability proofs are invited to submit a tender in CHF.
Award criteria
ZK 1
40 %Price criterion
TEXFY assessment: What this means: Price – what your offer costs. Usually the cheapest offer gets full points, more expensive ones fewer.
Price
ZK 2
15 %
TEXFY assessment: What this means: Personnel – how qualified and experienced the people carrying out the contract are, such as the project manager.
Quality of the tenderer, experience of key persons
Subdivided into:
- ZK2.1: Technical Manager, weighting 10%
- ZK2.2: Assembly Manager / Site Manager, weighting 5%
ZK 3
15 %
TEXFY assessment: What this means: Plausibility – whether the price and the service of your offer fit together convincingly.
Quality / plausibility of the tender
Subdivided into:
- ZK3.1: Technical report incl. risk analysis, weighting 10%
- ZK3.2: Sustainability analysis, weighting 5%
ZK 4
15 %
Construction time
ZK 5
15 %
TEXFY assessment: What this means: Plausibility – whether the price and the service of your offer fit together convincingly.
Quality and plausibility of the construction schedule with construction workflows
The details concerning award criteria must be submitted together with the (specified) tender documents:
Price evaluation
The lowest adjusted tender receives the maximum grade (5). Tenders whose price is 30% or more above the lowest tender receive a grade of 0. Evaluation in between is linear (rounded to 2 decimal places). Any offered cash discounts are not taken into account in the price evaluation.
Grading of the remaining award criteria
The evaluation is always carried out with grades from 0 to 5:
0 = Cannot be assessed; no information provided
1 = Very poorly fulfilled; insufficient, incomplete information 2 = Poorly fulfilled; information without sufficient project reference 3 = Fulfilled, corresponding to the requirements of the tender 4 = Well fulfilled; Qualitatively good
5 = Very well fulfilled; Qualitatively excellent, very large contribution to achieving the objective
If a main criterion consists of sub-criteria, these will be graded. The score of the main criterion results from the sum of the grades of the sub-criteria multiplied by their weighting.
Points calculation: Sum of all grades multiplied by their weighting (maximum score: grade 5 x 100 = 500 points).
Conditions
12 conditions
- Bidding consortia
- Allowed
Permitted. Lead management must be assigned to a company within the bidder consortium. The other participants must be disclosed in the tender documents. Members of the bidder consortium may not be replaced after submission of the tender.
- Subcontractors
- Allowed
Permitted. Subcontractors may be involved up to a max. of 50%. They must be listed accordingly in the tender documents. Information regarding subcontractors will be co-evaluated. The characteristic service must essentially be provided by the contractor.
- Contract extension
- Possible
An extension depends on the availability of funds, project progress, any project changes, line approval and not least on the quality of the services already provided.
- Dialogue
- Not provided for
- Securities and guarantees
In accordance with section 5 of the intended contract document.
- Terms of payment
45 days after receipt of invoice at ASTRA.
- Costs included in the bid price
Remuneration and prices include all services mentioned in the tender documents and necessary for the fulfillment of the contract.
The reallocation of unit prices into lump-sum items, such as site installations, is strictly prohibited.
The contractor must fill in all items of the bill of quantities; they shall write "0" for all items for which they formally waive the indication of an amount as well as the right to claim subsequent remuneration for the service in question. Such an entry must be justified in the technical report.
Items with the figure "0" without a comprehensible justification defined in the contractor's technical report are not permitted and will lead to exclusion at the latest during the formal examination (in the absence of subsequent submission/bid clarification).
In particular for the treatment, transport, and recycling of waste, these items must be listed individually for the waste included in the disposal concept. Lump sums are only permitted with justification and calculation bases.
If items for the treatment, transport, and recycling of waste are offered with "0", the client reserves the right to choose the disposal facilities themselves.
Negative unit prices are permitted, but require a comprehensible justification in the contractor's technical report. If the justification is missing at the latest during the formal examination (subsequent submission / bid clarification), this will lead to exclusion.
Supervision and management costs as well as the time-related costs for personnel transport must not be included in the site installation costs, but must be included in the unit prices in accordance with the SIA calculation scheme.
Likewise, all final cost surcharges such as technical and commercial management, site management, and financial costs must be recorded in the corresponding categories in the SIA calculation scheme. These costs must under no circumstances be included in the site installations.
- Terms and conditions
According to the intended contract document.
- Other requirements
1. Subject to the project's readiness for procurement and the availability of funds;
2. The preparation of bids will not be remunerated. The tender documents will not be returned;
3. Tender documents are available in German. In the event of contradictions between the versions, the German version shall prevail.
4. Due to financing that is not yet secured in terms of time, a postponement of the works is possible. In the event of a postponement, this will be by a full calendar year. However, the structuring of deadlines, dates, and programs within the construction years remains unchanged. In the event of a postponement, the contractor has no entitlement to compensation apart from inflation.- Previously involved bidders
Keine.
- Bidders from states outside the WTO agreement
Keine.
Conditions of participation
Criterion 1
TEXFY assessment: What this means: Obligations – whether your company is registered and complies with taxes, social security contributions and working conditions.
Compliance with all legal requirements, in particular confirmation of compliance with the provisions applicable in Switzerland regarding occupational health and safety and equal pay for men and women. Compliance with the required bid structure according to the doc. cover sheet bid for construction contracts. Unrestricted acceptance of the provisions in the intended contract document as well as the General Terms and Conditions (GTC) of the Confederation according to the tender documents.
Documents to submit
4 pieces of evidence according to the publication
For the tenderer: 1 reference project regarding completed works with comparable complexity and from the same specialist area.
For the tenderer: Proof of turnover for the years 2023-2025; the annual turnover of the tenderer must be at least twice the annual turnover of the contract. Joint ventures may only add up the annual turnover of the respective companies in proportion to their participation in the joint venture.
For the key person "Technical Manager": 1 reference object regarding completed works in an equivalent function or deputy function with comparable complexity and from the same specialist area.
For the tenderer: Proof that a maximum of 50% of the services are provided by subcontractors.
Official source
- simap project number
- 46149
- Publication number
- 46149-01
- Covered by international agreements
- Yes
- Notice of legal remedies
ShowHide
In accordance with Art. 56 Abs. 1 of the Federal Act on Public Procurement (BöB), an appeal in writing may be lodged against this ruling within 20 days of notification with the Federal Administrative Court, P.O. Box, 9023 St. Gallen. The appeal must be submitted in duplicate and must contain the requests, the grounds thereof with specification of evidence, as well as the signature of the appellant or their representative. A copy of this ruling and available evidence must be enclosed.
The provisions of the Federal Act on Administrative Procedure (VwVG) regarding the suspension of deadlines shall not apply pursuant to Art. 56 Abs. 2 BöB.
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.