Review of the cost study 2026 (KS26) - Decommissioning and postoperational costs: Review of the cost calculation / Disposal costs: Review of the cost calculation

Contracting authority
Stilllegungsfonds für Kernanlagen | Entsorgungsfonds für Kernkraftwerke STENFO
Place
Canton BE
Submission deadline
No deadline given
Published
10.12.2025
Procedure
Selective procedure
Type
Service
Project number
11137
CPV code
71244000 Calculation of costs, monitoring of costs

Description

The scope of the contract includes the review of cost calculations related to decommissioning and post-operational costs (Lot 1) as part of the 2026 cost study:

  • Verification of compliance with the requirements for the preparation of KS26 (in particular with regard to cost breakdown and cost structures);
  • Verification of compliance with the performance assumptions and unit prices and costs on which the cost calculation is based (review of adjustments and deviations from KS21):
  • Review of the plausibility and traceability of cost levels:
  • The methodology of risk assessments and evaluations, the methodology for determining forecast inaccuracies and the evaluation of hazards and opportunities must be checked for plausibility and comprehensibility. At the same time, it must be verified whether this work has been carried out in accordance with «best practice standards»;
  • Communication with the Swiss Federal Nuclear Safety Inspectorate (ENSI) and the experts «safety margin» on the determination of hazards (cost no. 5) and opportunities (cost no. 6) (statements on probability of occurrence and extent of damage) as well as cost no. 7 (listing of hazards and opportunities not taken into account) with justification for not taking them into account in cost no. 5 or 6;
  • The delimitation of the individual cost levels in terms of content and costs must be reviewed (no duplication, no implausible allocation of risks to a cost level);
  • The cost calculations of KS26 (decommissioning costs) must be checked for plausibility against the costs of comparable projects at foreign NPPs;
  • The plausibility check must be carried out at the level of the individual cost elements and on the basis of empirical values;
  • Reporting in accordance with relevant requirements.