The price is not published under public procurement law.
Awarded
- Construction and installation
- NPK 113 Site establishment
- NPK 117 Demolition and dismantling
- +4
Rte de Chenaule, partie Sud
- Location
- Canton VD
- Requesting office
- Municipalité de Pully
Awarded
Awarded to
- FFA SA, Villars-Ste-CroixPrice not published
What is being procured?
Scope of work
Renouvellement des collecteurs d'évacuation des eaux clairs, extension du réseau d'électricité basse tension et réfection des infrastructures routières.
Quantités principales
Fouilles : 2’800 m3
Fouille en pleine masse : 1’200 m3
Blindage : 3’500 m2
Conduite d’eau potable : 240 m
Tube PELD : 1’600 m
Enrobés : 2’500 to
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Civil engineering
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- NPK 113 – Site establishment
- NPK 117 – Demolition and dismantling
- NPK 151 – Construction works for utility mains
- NPK 222 – Segmental (sett, block and flag) paving, kerbing and steps
- NPK 223 – Asphalt and concrete pavements
- NPK 237 – Drainage and sewer systems
- CPV
- CPV 45222000 – Construction work for engineering works except bridges, tunnels, shafts and subways
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
Go to the official tender(simap.ch, opens in a new tab)
- simap project number
- 1818
- Publication number
- 1818-02
- Covered by international agreements
- No
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.