- Construction and installation
- NPK 111 Daywork
- NPK 112 Testing and inspection
- +9
Flood protection Village Alpthal - Preliminary measures
- Procuring office
- Bezirk Schwyz - Abteilung Umwelt
At a glance
- 16.11.2026, 16:005 days left
- Construction and installation
- Open procedure
- Not stated
Is a bid worth it?
With a free profile, TEXFY checks this tender against your services and cantons: a relevance grade from A to E and a recommendation with reasons.
TEXFY assessment: Risks and notes
Tight deadlineImportant
5 days left to submit. Plan documents, proofs and delivery now.
Bid languageNote
The bid must be in German.
References requiredNote
For eligibility you need comparable reference projects. Check number, age and size.
2 more notes
Paper onlyGood to know
Submission by post or in person. Allow for delivery and check whether the postmark or receipt counts.
Price counts 50 %Good to know
Price makes up 50 % of the evaluation.
What is being procured?
Scope of work
Die Ausführung des Hochwasserschutzprojekts wird in zwei separaten Losen erstellt.
- Los Vormassnahmen
- Los Hauptarbeiten
Die vorliegende Ausschreibung umfasst die Arbeiten vom Los Vormassnahmen. Das Los Hauptarbeiten ist nicht Bestandteil dieser Ausschreibung.
Die Arbeiten beim Los Vormassnahmen umfassen folgende Massnahmen:
Geissbergbach
Oberhalb der Hochweidstrasse wird ein neuer Geschiebesammler erstellt. Der Einlaufbereich wird mit Blöcken in Beton ausgeführt. Als Auslaufbauwerk wird eine Betonmauer mit eingesetzten Stahlträgern (Rechen) erstellt. Der Unterhaltszugang zum Geschiebesammler erfolgt ab der Hochweidstrasse über eine neue Erschliessungsstrasse mit Schotterrasen. Der best. Durchlass Hochweidstrasse bleibt unverändert.
Oberhalb des Kiessammlers wird das Gerinne mittels einer neu erstellten Beckenstruktur mit Schwellen, bestehend aus 1.5 bis 2.5 Tonnen schweren Blöcken in Beton, auf den nötigen HW-Querschnitt ausgebaut. Die Blöcke in den Böschungen werden nicht einbetoniert. Weiter oben, ausgangs des Waldes, wird mittels Terrainanpassung ein Ablenkdamm erstellt.
Hochweidbach
Oberhalb der Hochweidstrasse wird das Gerinne ausgebaut und der Abflussquerschnitt vergrössert, um das Wasser fassen zu können. Im steilen oberen Bereich wird der Bach durch Blöcke und Schwellen als Beckenstruktur gestaltet.
Mattlibach
Im Oberlauf des Mattlibachs wird ein Geschiebesammler mit einem neuen Auslaufbauwerk erstellt. Der Einlaufbereich wird mit Blöcken in Beton ausgeführt. Das Auslaufbauwerk wird mittels Rechenkosruktion ausgebildet und schliesst an die bestehende Eindolung an.
Karlismattbach
Oberhalb des Siedlungsrandes am Haggeneggweg wird ein neuer Geschiebesammler erstellt. Der Einlaufbereich wird mit Blöcken in Beton ausgeführt. Als Auslaufbauwerk wird eine Betonmauer mit eingesetzten Stahlträgern (Rechen) erstellt. Für den Bau sind vorgängig Umlegungen von Werk- und Quellwasserleitungen erforderlich.
Der Unterhaltszugang zum Geschiebesammler erfolgt über eine neue Erschliessungsstrasse mit Schotterrasen.
Unterhalb des Kiessammlers wird das Gerinne mittels einer neu erstellten Beckenstruktur mit Schwellen, bestehend aus 1.5 bis 2.5 Tonnen schweren Blöcken in Beton, auf den nötigen HW-Querschnitt ausgebaut. Die Blöcke in den Böschungen werden nicht einbetoniert.
Der kleine, bereits vorhandene Kiessammler bleibt unverändert bestehen.
Die detaillierten Massnahmen und genauen Abgrenzungen sind in den Projektpläne ersichtlich.
Die einzelnen Baustellen sind auf verschiedene Teilperimeter verteilt und nicht zusammenhängend. Die Zwischentransporte von Aushubmaterial und Humus sind teilweise Bauplatzübergreifend, wobei die öffentlichen Strassen und Grundstücke/Strassen Dritter gequert werden müssen.
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Civil engineering
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- NPK 111 – Daywork
- NPK 112 – Testing and inspection
- NPK 113 – Site establishment
- NPK 116 – Felling and site clearance
- NPK 117 – Demolition and dismantling
- NPK 151 – Construction works for utility mains
- NPK 211 – Excavation and earthworks
- NPK 213 – Hydraulic engineering
- NPK 221 – Sub-bases for transport routes
- NPK 237 – Drainage and sewer systems
- NPK 241 – In-situ concrete construction
- OAG 4.6.1 – Watercourse channel/bank improvement
- CPV
- CPV 45000000 – Construction workCPV general: general code without a field
- CPV 45240000 – Construction work for water projects
- Options
- Not provided for
- Variants
- Admitted
Der Auftrageber behält sich vor, auf eingereichte Varianten ohne weitere Begründung nicht einzutreten, respektive diese nicht zu berücksichtigen.
- Partial offers
- Not admitted
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Dates
- Published
- 16.10.2026
- Questions untilpast
- 23.10.2026
Fragen zur Ausschreibung sind schriftlich nur über das entsprechende Simap Forum bis spätestens Freitag 23. Oktober 2026 zu stellen. Die Antworten werden im gleichen Forum bis spätestens Mittwoch 28. Oktober 2026 veröffentlicht. Auf anderen Wegen eingegangene Fragen werden nicht beantwortet.
- Submission deadlinenext
- 16.11.2026, 16:00
- Opening of bids
- 17.11.2026, 11:00, 6430 Schwyz, public
Bezirk Schwyz
Abteilung Umwelt (2. Stock)
Strehlgasse 15
6430 Schwyz - Bid valid
- until 16.05.2027
- Contract
- 01.01.2027 to 31.12.2027
Special deadlines and formal requirements
Special deadlines and formal requirements
Das Angebot muss spätestens zum Eingabezeitpunkt (Datum Uhrzeit) physisch beim Bezirk Schwyz eingetroffen sein. Bei Angeboten, die per Post eingereicht werden, trägt der Absender das Risiko, dass das Angebot fristgerecht beim Bezirk Schwyz eintrifft.
Submission & documents
By post or delivery in person
Bezirk Schwyz - Abteilung UmweltErnst RothPostfach 606431 SchwyzSource: simap data
- Documents on simap.ch (after signing in)
- German
- German
- Free of charge
- Through the question forum on simap.ch (registration as a bidder required). Go to the official tender (simap.ch, opens in a new tab)
Participation & award
In the documents according to the source: Content only in the tender documentsIn the tender documents: Conditions of participation.
Participation & suitability
2 eligibility criteria
EK 1
Eigenleistung
Die Eigenleistung der Unternehmung resp. ARGE muss in Franken mindestens 60 % der Offertsumme betragen. Die Unternehmung resp. ARGE hat anzugeben, welche NPK Kapitel oder Teile davon sie als Eigenleistung erbringt (Nachweis auf «Formular Eigenleistung»).
EK 2
TEXFY assessment: What this means: Experience – whether you have carried out comparable contracts, shown with references.
Firmenreferenzen (Unternehmung / ARGE)
Es sind zwei Referenzen (Angaben im Formular «Referenznachweis Unternehmung / ARGE») beizubringen.
Die Referenzen weisen nach, dass die Unternehmung resp. ARGE innerhalb der letzten acht Jahre (Bauende 2018 oder später) mit der vorliegenden Aufgabe vergleichbare Projekt realisiert hat.
Die Vergleichbarkeit des Referenzprojektes für die Firmenreferenz beinhaltet:
1. Wasserbauprojekt mit Bausumme mind. CHF 0.5 Mio. exkl. MWST
2. Bau eines Geschiebesammlers mit Sperren/Rechen und Rückhaltevolumen >100m³
Die Referenzen müssen vom federführenden Anbieter oder einem ARGE-Mitglied erbracht werden.
Award criteria
ZK 1 - Preis
50 %max. 50 pointsPrice criterion
TEXFY assessment: What this means: Price – what your offer costs. Usually the cheapest offer gets full points, more expensive ones fewer.
Die günstigste bereinigte Offertsumme erhält 50 Punkte. Die Offertsummen die 50% oder mehr vom tiefsten Angebot abweichen, erhalten 0 Punkte. Dazwischen werden die Punkte linear vergeben.
ZK 2 - Qualität / Referenzen
30 %max. 30 points
TEXFY assessment: What this means: Experience – whether you have carried out comparable contracts, shown with references.
Gewertet werden die Referenzen der Unternehmung/ARGE. Die minimalen Anforderungen sind im Kapitel 2.4.1 Eignungskriterien definiert. Zusätzliche Punkte ergeben die Grösse der Baustellen (Bausumme, Volumen Geschiebesammler), der Nachweis von umfangreichen Blocksatz- und Erdarbeiten / Dammschüttungen im Wasserbauprojekt und die technischen Anforderungen der genannten Baustellen, beispielsweise die technischen Schwierigkeiten bei der Ausführung der Sperren/Rechen, die Anforderungen an die Wasserhaltung oder dgl.
Die Auswertung erfolgt anhand der ausgefüllten Formulare «Referenznachweis Unternehmung/ARGE».
Für die Bewertung der Referenzen werden nur die Angaben auf diesen Formularen berücksichtigt. Die Formulare müssen vollständig ausgefüllt werden. Unvollständige Angaben werden nicht berücksichtigt resp. ergeben Abzüge in der Bewertung.
Für das ZK 2 werden maximal 30 Punkte verteilt.
ZK 3 - Technischer Bericht
20 %max. 20 points
Unter diesem Zuschlagskriterium werden die zusätzlich verlangten Unterlagen zum technischen Bericht gemäss Kapitel 2.9 (Besond. Bestimmungen) und alle anderweitigen Angaben des Unternehmers zum Angebot ausgewertet.
Conditions
4 conditions
- Bidding consortia
- Allowed
Mehrere Anbieter können als Arbeitsgemeinschaft ein gemeinsames Angebot einreichen. Es werden nur Arbeitsgemeinschaften gemäss Art. 28 SIA 118 akzeptiert. ARGE-Partner dürfen sich nur in einer Bietergemeinschaft beteiligen.
- Subcontractors
- Allowed
Der Unternehmer wird ausdrücklich darauf aufmerksam gemacht, dass die Subunternehmer zum Zeitpunkt des Arbeitsbeginns definitiv bestimmt und bezeichnet sein müssen. Der Unternehmer muss den Bauablauf mit den Subunternehmern so koordinieren, dass ein reibungsloser Ablauf möglich ist.
Spezialisten und/oder Subunternehmer, welche nicht ARGE-Partner sind, dürfen sich mit mehreren Bietergemeinschaften bewerben - Contract extension
- Possible
- Dialogue
- Not provided for
Documents to submit
1 piece of evidence according to the publication
Es sind zwei Referenzen (Angaben im Formular «Referenznachweis Unternehmung / ARGE») beizubringen.
Die Referenzen weisen nach, dass die Unternehmung resp. ARGE innerhalb der letzten acht Jahre (Bauende 2018 oder später) mit der vorliegenden Aufgabe vergleichbare Projekt realisiert hat.
Die Vergleichbarkeit des Referenzprojektes für die Firmenreferenz beinhaltet:
1. Wasserbauprojekt mit Bausumme mind. CHF 0.5 Mio. exkl. MWST
2. Bau eines Geschiebesammlers mit Sperren/Rechen und Rückhaltevolumen >100m³
Die Referenzen müssen vom federführenden Anbieter oder einem ARGE-Mitglied erbracht werden.
Official source
- simap project number
- 45929
- Publication number
- 45929-01
- Covered by international agreements
- No
- Notice of legal remedies
ShowHide
Gegen die Ausschreibung kann innert 20 Tagen seit der Publikation auf www.simap.ch beim Verwaltungsgericht des Kantons Schwyz, Postfach 2266, 6431 Schwyz, schriftlich und begründet Beschwerde eingereicht werden (Art. 52 ff. IVöB). Es gelten keine Gerichtsferien.