Vorteilhaftestes Angebot unter Berücksichtigung der bekannt gegebenen Zuschlagskriterien. Das Angebot weist insbesondere beim Kriterium Preis Vorteile auf.
- Construction and installation
- BKP 224 Roofing
- NPK 351 Roof plumbing: roof drainage and flashings
- +4
Neubau Zivilschutz Ausbildungszentrum Meiersboda, Chur / BKP 224 Bedachungsarbeiten
- Location
- Canton GR
- Procuring office
- Hochbauamt Graubünden
Awarded
Awarded to
- Burkhardt Gebäudehülle AG, MaienfeldCHF 464’062.80
What is being procured?
Scope of work
Das Gebäude wird Minergie-A/P-ECO zertifiziert.
Holzgebäude dreigeschossig, 34m lang, 24m breit und 11m hoch
Spezifikationen:
Bedachungsarbeiten Flachdach rund 950 m2 inkl.
- Spenglerarbeiten
- Blitzschutz
- RWA-Oberlicht
- Scherentreppe
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 224 – Roofing
- NPK 351 – Roof plumbing: roof drainage and flashings
- NPK 357 – External lightning protection systems
- NPK 364 – Flat roofing
- NPK 365 – Glazed elements in roofs
- NPK 367 – Fall prevention for inspection and maintenance on roofs
- CPV
- CPV 45210000 – Building construction work
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 12433
- Publication number
- 12433-02
- Covered by international agreements
- Yes
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.