Das Angebot des Zuschlagsempfängers liegt beimZuschlagskriterium Preis an erster Stelle und ist aufgrund der Bewertung aller in der Ausschreibung festgelegten Zuschlagskriterien auch das vorteilhafteste.
- Construction and installation
- NPK 111 Daywork
- NPK 112 Testing and inspection
- +7
Lenzburg-Villmergen IO/AO, K247 und K123
- Location
- Canton AG
- Procuring office
- Abteilung Tiefbau (ATB)
Awarded
Awarded to
- KIBAG Bauleistungen AG, OftringenCHF 860’322.65
What is being procured?
Scope of work
Erstellen einer durchgängigen Kabelrohranlage / ATB-Rohrverbindung von Lenzburg bis Villmergen ohne Einzug eines LWL-Kabels auf der gesamten Länge.
Kabelpflugarbeiten 4'200 m1
Konventionelle Gräben 2'600 m1
Gesteuerte Spülbohrungen 115 m1
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Civil engineering
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- NPK 111 – Daywork
- NPK 112 – Testing and inspection
- NPK 113 – Site establishment
- NPK 117 – Demolition and dismantling
- NPK 151 – Construction works for utility mains
- NPK 152 – Pipe jacking
- NPK 221 – Sub-bases for transport routes
- NPK 222 – Segmental (sett, block and flag) paving, kerbing and steps
- NPK 223 – Asphalt and concrete pavements
- CPV
- CPV 45000000 – Construction workCPV general: general code without a field
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 18479
- Publication number
- 18479-02
- Covered by international agreements
- No
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.