Awarded
- Construction and installation
- BKP 222 Roof plumbing
- BKP 223 Lightning protection systems
- +3
562.67 Schiffbau Zürich -Sanierung Foyerdach
- Location
- Canton ZH
- Procuring office
- Schiffbau Immobilien AG
- Requesting office
- arc Consulting + Architektur AG
Awarded
Awarded to
- Riget AG, Pfäffikon SZCHF 277’191.95
What is being procured?
Scope of work
Sanierung eines geneigten Flachdachs aus dem Jahr 2000 (ca.). Abbruch + Entsorgung des bestehenden Dachaufbaus bis auf die tragenden Holzwerkstoffplatten. Neuer Dachaufbau ab Dampfbremse bis/mit extensive Begrünung inkl. Ansaat und Erstpflege. Die Bauarbeiten müssen in der Spielpause des Schauspielhauses zwischen 30.06.2025 - 08.08.2025 ausgeführt werden.
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 222 – Roof plumbing
- BKP 223 – Lightning protection systems
- BKP 224 – Roofing
- NPK 351 – Roof plumbing: roof drainage and flashings
- NPK 364 – Flat roofing
- OAG 1.8 – Culture
- OAG 1.9 – Hospitality
- CPV
- CPV 45000000 – Construction workCPV general: general code without a field
- CPV 45200000 – Works for complete or part construction and civil engineering work
- CPV 45300000 – Building installation work
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
Go to the official tender(simap.ch, opens in a new tab)
- simap project number
- 14338
- Publication number
- 14338-02
- Covered by international agreements
- No
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.