Die Firma Vontobel Abbruch + Aushub AG reichte das vorteilhafteste Angebot ein. Es erfüllt die Zuschlagskriterien nach Art. 29 Interkantonale Vereinbarung über das öffentliche Beschaffungswesen (IVöB) am besten.
- Construction and installation
- BKP 112 Deconstruction
- BKP 201 Basement excavation
- +5
Neubau Gemeindehaus Münsingen - BKP 201 Baugrubenaushub
- Location
- Canton BE
- Procuring office
- Gemeinde Münsingen, Abteilung Bau
Awarded
Awarded to
- Vontobel Abbruch + Aushub AG, BernCHF 796’129.00
What is being procured?
Scope of work
Die beiliegende Submission umfasst die kompletten Ausführungsarbeiten gemäss Beschrieb BKP 201
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 112 – Deconstruction
- BKP 201 – Basement excavation
- NPK 110 – Enabling, site clearance and demolition works
- NPK 120 – Protective and ancillary works
- NPK 160 – Excavation support and dewatering
- NPK 210 – Ground engineering
- NPK 241 – In-situ concrete construction
- OAG 1.3.7 – Office and administrative building
- CPV
- CPV 45110000 – Building demolition and wrecking work and earthmoving work
- CPV 45112000 – Excavating and earthmoving work
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 30079
- Publication number
- 30079-02
- Covered by international agreements
- Yes
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.