Beste Erfüllung der Zuschlagskriterien nach Art. 51 Abs. 3 BöB, unter Berücksichtigung von Art. 51 Abs. 4.
- Construction and installation
- BKP 29 Professional fees
Energy storage channel and EWS, BKP 294 HVAC-E-GA Engineer
- Location
- Canton ZH
- Procuring office
- Flughafen Zürich AG - Energie 2040
Awarded
Awarded to
- Anex Ingenieure AG, ZürichCHF 282’676.00
- Lier Energietechnik, GlattbruggCHF 431’016.00
What is being procured?
Scope of work
Planung Heizung/Kälte, Elektro, Gebäudeautomation und Gesamtleitung der Anergie Speichersysteme für die neue Energiezentrale Mitte. Optimale Einbindung der verschieden Quellen wie Rinne (Tiefengrundwasserbrunnen), Energiepfähle, Erdwärmesonden und Abwärme weiterer Kälteanlagen. Die Aufgaben sind in zwei Lose aufgeteilt, Los 1 Anergie Rinne und Los 2 Anergie EWS, Teilangebote pro Los sind zugelassen.
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 29 – Professional fees
- OAG 1 – Building
- CPV
- CPV 71000000 – Architectural, construction, engineering and inspection services
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 14739
- Publication number
- 14739-02
- Covered by international agreements
- No