Prestations de planificateur général et d’ingénieur civil pour le renouvellement des installations de sécurité de Colondalles et Fontanivent sur la ligne ferroviaire du MOB
- Location
- Place open, contracting authority in canton VD
Awarded
Awarded to
- Project Partners Ltd Consulting Engineers, MontagnolaCHF 220’536.00
What is being procured?
Scope of work
Le marché comprend les prestations de planification et de direction générale du projet, les prestations d'études et de direction des travaux, pour les phases partielles SIA 41 à 53 du renouvellement des installations de sécurité de Colondalles et Fontanivent sur la ligne ferroviaire du MOB. Les prestations couvrent le génie civil, la géotechnique et la mensuration.
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Service
- Procedure
- Open procedure
- Trades
- Not evident from the available publication data.
- CPV
- CPV 71000000 – Architectural, construction, engineering and inspection services
- CPC
- CPC 3d347dc3-c815-4ec1-8e39-637046ba6f27 – Architectural services; engineering services and integrated engineering services, urban planning and landscape architectural services; related scientific and technical consulting services; technical testing and analysis services
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
- simap project number
- 20428
- Publication number
- 20428-02
- Covered by international agreements
- Yes
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.