  • Construction and installation

TR1570, 220kV Mühleberg-St-Triphon, Demontage- und Montagearbeiten Freileitung zur Leitungssanierung

Published in German / French. Sign in and TEXFY shows the texts in English. Sign in

Location
Canton BE
Procuring office
Swissgrid AG - Engineering & Construction
Go to the official tender(simap.ch, opens in a new tab)

Awarded

According to the simap publication. Values that are not given are deliberately missing here.

Awarded to

As published on simap.ch: winner and price (with or without VAT, as stated).

  • Lot 1: Montage HTLS Leiterseile vom Unterwerk St-Triphon (1570x271) bis Mast 1570x237 (inkl.)Award of 02.07.20264 bids

    • Eduard Steiner AG Rikon, Rikon im TösstalCHF 3’626’386.72 incl. VAT
  • Lot 2: Montage HTLS Leiterseile vom Mast 1570x237 bis Mast 1570x162Award of 02.07.20264 bids

    • RELE GmbH, Ringgenberg BECHF 4’467’278.23 incl. VAT
  • Lot 3: Ersatz von Isolatorenketten zwischen Mühleberg und dem Unterwerk BotterensAward of 02.07.20264 bids

    • Eduard Steiner AG Rikon, Rikon im TösstalCHF 1’728’506.17 incl. VAT
Awards of this contracting authority

Justification

Sehr attraktiver Preis und sehr gute Erfüllung der qualitativen Zuschlagskriterien.

Awarded

Justification

Attraktiver Preis und gute Erfüllung der qualitativen Zuschlagskriterien.

Awarded

Justification

Attraktiver Preis und sehr gute Erfüllung der qualitativen Zuschlagskriterien.

What is being procured?

Scope of work

Language of the publication
  • Ersatz der Leiterseile durch HTLS (High Temperature Low Sag) - Leiterseile mit Carbonkern:

o 2 Systeme 220kV von Mast 1570x237 bis Unterwerk St-Triphon (1570x271)

o 1 System 65 kV (Romande Énergie), vom Mast 1570x237 bis Mast 1570x271

  • Ersatz von Porzellanisolatoren durch Silikonisolatoren, um die Isolatoren an aktuelle Produktstandards anzupassen (betrifft Isolatoren im Abschnitt Mast 1570x237 - Unterwerk St.Triphon (1570x271)).
  • Anpassung der Verteilung von Phasenabstandhaltern (zwischen Leiterseilen) im gemeinsamen Abschnitt 65kV (Romande Energie) / 220kV (Swissgrid) vom Mast 1570x237 bis Mast 1570x271.
  • Punktuelle Verstärkung ausgewählter Masten.
  • Nachspannen des Erdseils (mit LWL) auf einigen Abspannstrecken.

Key facts, codes and options

Type of contract
Construction and installation
Type of construction
Building construction
Construction service
Execution
Procedure
Open procedure
Trades
Not evident from the available publication data.
CPV
  • CPV 45232210 – Overhead line construction
Options
Not evident from the available publication data.
Variants
Not evident from the available publication data.
Partial offers
Not evident from the available publication data.

TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.

Official source

Go to the official tender(simap.ch, opens in a new tab)
simap project number
31870
Publication number
31870-03
Covered by international agreements
Yes

Checked against simap: 10.11.2026, 18:02

Export

This is not an official publication. Only the data published on the platform www.simap.ch is authoritative. Dies ist keine amtliche Veröffentlichung. Massgebend sind die auf der Plattform www.simap.ch veröffentlichten Daten. Anyone who reuses this data complies with the conditions of simap.ch: terms, section 6.

Contract awards in Bern: monthly reports
Report a data error

Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.

Kind of error

Please do not write personal data into it. If you are signed in, we store the report with your account.