Awarded
- Construction and installation
- BKP 135.1 Electricity
- BKP 23 Electrical installations
- +3
Transformation EMS de l'Orme - 23000 - Installations électriques
- Location
- Canton VD
- Procuring office
- Fondation de l'Orme (AAPA SA)
- Requesting office
- Fondation de l'Orme
Awarded
Awarded to
- Maréchaux électricité S.A., CrissierCHF 1’422’704.00
What is being procured?
Scope of work
Travaux d'installations électriques dans le cadre de la Transformation de l'EMS de l'Orme. Le bâtiment doit attendre une performance équivalente au standard Minergie ECO
Étendu du marché :
- Surface de plancher (SP) : 4'464 m2
- Surface nette (SN) : 3'931 m2
- Surface de référence énergétique (SRE) : 3'991 m2
- Volume bâti (VB) : 13'261 m3
- Nombre de chambres/lits : 58
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- BKP 135.1 – Electricity
- BKP 23 – Electrical installations
- BKP 33 – Electrical installations
- BKP 443 – Electrical installations
- NPK 500 – Electrical installations
- OAG 1.6.1 – Retirement and nursing home
- CPV
- CPV 45310000 – Electrical installation work
- Options
- Not evident from the available publication data.
- Variants
- Not evident from the available publication data.
- Partial offers
- Not evident from the available publication data.
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Official source
Go to the official tender(simap.ch, opens in a new tab)
- simap project number
- 6585
- Publication number
- 6585-02
- Covered by international agreements
- Yes
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.