- Construction and installation
Renovation of the HV-MV substation La Foretaille - Lot 21: Cleaning phase 1 to 6
- Procuring office
- Services industriels de Genève (SIG) - Direction Achats
- Requesting office
- Services industriels de Genève (SIG) - Direction Distribution Electricité et Comptage (DEC)
At a glance
- 16.11.2026, 12:005 days left
- Construction and installation
- Open procedure
- In the documents
- In the documents
Is a bid worth it?
With a free profile, TEXFY checks this tender against your services and cantons: a relevance grade from A to E and a recommendation with reasons.
TEXFY assessment: Risks and notes
Mandatory site visit: check the dateImportant
According to the publication, attending is mandatory; date and place are in the note. Check there whether the visit is still ahead: missing it risks exclusion.
Tight deadlineImportant
5 days left to submit. Plan documents, proofs and delivery now.
Bid languageNote
The bid must be in French.
4 more notes
Securities per contractGood to know
Whether a surety or guarantee is needed is set out in the contract or the documents. Check there.
Subcontracting limitedGood to know
The publication limits subcontracting, for example by share or by requiring consent.
Paper onlyGood to know
Submission by post or in person. Allow for delivery and check whether the postmark or receipt counts.
No variantsGood to know
Only the requested bid counts; your own alternative solutions are not allowed.
What is being procured?
Scope of work
Travaux de de nettoyage de la Foretaille, chantier et zone de vie
Key facts, codes and options
Key facts, codes and options
- Type of contract
- Construction and installation
- Type of construction
- Building construction
- Construction service
- Execution
- Procedure
- Open procedure
- Trades
- Not evident from the available publication data.
- CPV
- CPV 45452000 – Exterior cleaning work for buildings
- CPV 90910000 – Cleaning services
- Options
- Not provided for
- Variants
- Not admitted
- Partial offers
- Not admitted
TEXFY assessment: Products, installations, quantities, technical specifications and exclusions are not structured fields of the publication. TEXFY does not analyse the free text on them: check the original text and the tender documents.
Dates
- Published
- 07.10.2026
- Questions untilpast
- 02.11.2026
- Submission deadlinenext
- 16.11.2026, 12:00
- Bid valid
- 180 days after the deadline
- Execution
Selon le dossier d'appel d'offres
Site visit
Mandatory according to the publicationUne visite du site d’exécution est prévue durant la présente procédure :
30.10.2026 à 9h
Chemin des Clys 10, 1293 Bellevue
Matthieu Thévenaz
EPI obligatoire (casque, chaussures de sécurité, chasuble et pantalon)
Merci de vous inscrire auprès de matthieu.thevenaz@sig-ge.ch avant le 27.10.2026
MERCI DE PRENDRE VOS EPI POUR LA VISITE
Au vu de la particularité du marché, la visite du site est obligatoire par le fait que des informations ne peuvent être fournies autrement que par cette démarche.
Le fait qu’un soumissionnaire dépose une offre sans avoir participé à la visite obligatoire entraîne l’exclusion de son offre.
Submission & documents
By post or delivery in person
Services industriels de Genève (SIG) - Direction AchatsJérémy CalzolariChemin du Château-Bloch 21219 Le LignonSource: simap data
Special submission route
Le soumissionnaire doit déposer son offre sous pli fermé, soit par poste, soit en déposant directement à l’accueil SIG Lignon
Il appartient au soumissionnaire de tout mettre en œuvre pour respecter cette échéance. Le cachet postal ne fait pas foi.
Source: simap data
- Documents on simap.ch (after signing in)
- French
- French
- Free of charge
- Through the question forum on simap.ch (registration as a bidder required). Go to the official tender (simap.ch, opens in a new tab)
Participation & award
In the documents according to the source: Content only in the tender documentsIn the tender documents: Suitability criteria, Award criteria, Conditions of participation, Documents to submit.
Conditions
7 conditions
- Bidding consortia
- Allowed
- Subcontractors
- Allowed
La sous-traitance de rang 1 est admise. Les sous-traitants doivent également respecter toutes les conditions de participation. Le cas échéant, la part de sous-traitance ne doit pas dépasser le 20 % de l’ensemble du marché. Le soumissionnaire devra indiquer sur l’annexe R15S, quels sont les travaux ou prestations qui seront sous-traités, ainsi que le nom et l’adresse des sous-traitants auxquels il entend recourir. Le soumissionnaire devra joindre également les attestations exigées dans le dossier d’appel d’offres pour le sous-traitant concerné.
Un sous-traitant ne peut pas à son tour sous-traiter une partie du marché (sous-sous-traitance interdite). Le droit cantonal demeure réservé à cet égard.
Le non-respect de ces exigences amènera l’adjudicateur à prendre une décision d’exclusion des offres concernées, soit celle où le sous-traitant intervient comme soumissionnaire et celle du soumissionnaire proposant ledit sous-traitant. - Contract extension
- Not provided for
- Dialogue
- Not provided for
- Securities and guarantees
Selon l'ébauche de contrat SIG et les les conditions générales d'achats SIG
- Terms of payment
Selon l'ébauche de contrat SIG et les les conditions générales d'achats SIG
- Terms and conditions
Seules les conditions générales d'achats SIG font foi
Official source
- simap project number
- 45463
- Publication number
- 45463-01
- Covered by international agreements
- Yes
- Notice of legal remedies
ShowHide
Le présent appel d’offres peut faire l’objet d’un recours auprès de la Chambre administrative de la Cour de justice, 10 rue Saint-Léger, case postale 1956, 1211 Genève 1, dans les dix jours dès sa publication. Le recours doit être signé, se référer au présent appel d'offres, contenir les conclusions dûment motivées avec indication des moyens de preuve.
More in the guide
Report a data error
Is something on this page wrong, missing or badly translated? We check every report. We correct our own classification and translations ourselves; what simap publishes can only be changed by the contracting authority.